Construction loan applications can be delayed when the contract, plans, approvals and finances do not match. A lender wants them all to tell the same story. Here are the mistakes that slow a construction loan down, and how to fix each one.
Applying Before the Building Contract and Council Approval Are Ready
A construction loan application is much stronger when the building contract, plans and council approval are in place. Lenders assess what they are funding, so lenders commonly ask for a signed fixed price building contract, the council plans and proof your builder is registered.
If the contract has vague allowances or the plans are still changing, the lender cannot confirm the cost of the build. A lender may ask for a revised valuation or more information. Sort the build price and approvals first, then lodge the application.
Do Deposit and Progress Payment Terms Match Queensland Rules?
In Queensland, the maximum deposit is generally 5 per cent for contracts of $20,000 or more, or up to 20 per cent where off-site work is more than 50 per cent of the contract price. Progress payments must be related to the work completed on site. A contractor cannot claim more than 50 per cent of the contract price, including the deposit, until at least 50 per cent of the on-site work is complete.
Payments above the contract amount or made early reduce protection under the Queensland Home Warranty Scheme. A lender may also query a payment schedule that does not match the work completed. Have the progress payment schedule checked against these limits before you sign. Many lenders base the draw schedule on the contract, but this varies, so ask your lender.
Assuming the Debt-to-Income Exemption Skips Serviceability
Construction of new dwellings is exempt from APRA's debt-to-income limit, but you still have to pass the lender's serviceability assessment. The exemption applies to a bank's lending portfolio and does not remove the test of whether you can afford the loan.
Banks regulated by APRA must assess your ability to repay at a rate at least 3 percentage points above the loan's rate. As an illustration only, at the example rate of 6.75% p.a., the assessment rate would be at least 9.75% p.a. Bonuses and overtime can also be discounted, with APRA noting that a prudent lender would apply discounts of at least 20 per cent to less stable income. Use our borrowing capacity tools to check where you stand before you commit to a design.
Ready to get started?
Book a chat with a Finance & Mortgage Broker at Mi Finance Broker today.
Forgetting Repayments During the Build
Repayments start small and grow as each stage is paid, so budget for the final size of the loan, not the first bill. Lenders set their own terms for repayment type during the build, so ask whether they only charge interest on the amount drawn down.
Consider a buyer with a $600,000 construction loan limit and an illustrative rate of 6.75% p.a. The slab stage draws $60,000, so the monthly interest is about $337.50 (60,000 x 6.75% / 12). By the time $300,000 has been drawn for frame and lock-up, monthly interest is about $1,687.50. At the final payment, with the full $600,000 drawn, it is about $3,375 a month, and that is before any move to principal and interest.
This buyer also pays rent during the build. They work out the peak overlap early and set aside a buffer for the months when rent and loan interest run together. The outcome is that no stage payment arrives as a surprise, and the builder is paid on time. Rates and terms depend on your lender and deposit, so use a calculator and confirm with your broker.
Leaving Progress Inspections and Drawdown Timing to Chance
Lenders set their own rules for inspections, the number of drawdowns, fees and how payments are released, and these differ between lenders.
If your builder invoices at a stage the lender has not yet inspected or approved, payment may be delayed. Ask your broker how the lender's inspection and release process works, and share it with your builder before work starts. Also check how long the lender allows for construction, so weather delays do not push you past it.
Not Comparing Lenders for Your Specific Build
A construction loan from one lender can differ widely from another in fees, drawdown rules and repayment options. A broker can compare options from the lenders on its panel against your build.
A custom design on an irregular block, an owner-builder project or a knock-down rebuild each raises different questions. Some lenders treat them differently, and a low-looking rate on paper may come with limits that do not suit your build. Comparing lenders takes time, and you should compare fees, rate terms and any broker remuneration, which should be disclosed to you. It is worth it when you want to build your dream home without reworking the finance halfway through.
If you are a first-time buyer, our first home buyers page explains how the process differs for you. The Gold Coast mortgage broker team can also help you plan the order of land settlement, contract signing and application.
If you are ready to start your construction loan application, call one of our team or book an appointment at a time that works for you. We will check your contract, approvals and budget together so the lender gets a clear picture from day one.
Frequently Asked Questions
What does a lender look at for a construction loan application?
A lender looks at your building contract, plans, council approval and builder details alongside your income and expenses. They need to confirm both the cost of the build and your ability to repay.
What is the maximum deposit on a Queensland building contract?
In Queensland, the maximum deposit is generally 5 per cent for contracts of $20,000 or more. It can be up to 20 per cent where off-site work is more than 50 per cent of the contract price.
Does the debt-to-income exemption mean I do not need to pass serviceability?
No. Construction of new dwellings is exempt from APRA's debt-to-income limit, but lenders must still assess your ability to repay. For APRA-regulated banks, that includes a buffer of at least 3 percentage points above the loan rate.
How do repayments work during construction?
Repayment terms during the build are set by each lender, so confirm yours. If interest is charged only on the amount drawn, repayments rise as each stage is paid.